Local shear wall demolition


Boulder Demolition/Concrete Demolition/Boulder Breaking/Concrete Breaking/Non Explosive/Non Blasting

Depending upon the height and width of the removal of the shear wall designed cutting line. The sub-cutting each weighing no more than 500 kilograms.Impact Drill the wall at the top side of the floor penetrated through the wire rope, and then hung on a 5 ton chain hoists;

In shear wall to be dismantled block drilling machine drilling through the wire rope, and then hung on a 5 ton chain hoist hook;The taut chain hoists;

Wall cutting machine or a row of holes drilling machine cutting wall, such as wall cutting machine to be installed in the wall track. General to dismantle the lower part of the wall blocks, and then remove the upper wall of the block;

Chain hoists will be cutting down the wall to the floor surface gently.

 

 